We have all permits and real work begins.
The step footings to connect the retaing footing to the other footings.
cousin dave showed up on his bike to have a look
we got two rivet busters to break down the existing wall to make way for our building block walls
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
Facebook Badge
ALR CONSTRUCTION
Promote Your Page Too
Followers
Blog Archive
►
2011
(8)
►
September
(7)
►
May
(1)
▼
2010
(143)
►
August
(1)
►
July
(10)
►
June
(24)
►
May
(16)
►
April
(21)
►
March
(41)
►
February
(20)
▼
January
(10)
Rain week.
Footings set
Phone conduit in.
Sewer signed off and backfilled.
footings for 8" block
electrical conduit...and sewer line
Tying steel, wall demo, and conduit setting...
Mechanical and Building Permits
Plumbing and Electrical Permits
We have all permits and real work begins.
►
2009
(30)
►
December
(10)
►
November
(2)
►
July
(3)
►
May
(4)
►
April
(1)
►
March
(3)
►
January
(7)
►
2008
(32)
►
December
(6)
►
November
(26)
About Me
View my complete profile
No comments:
Post a Comment