Thursday, January 21, 2010

Rain week.

Saturday, January 16, 2010

Tuesday, January 5, 2010

Tying steel, wall demo, and conduit setting...




Today we finished demo of the existing north wall and took the compressor back to PDQ. Continued to tie rebar. The inspector noticed a change in the plans from 8" cmu block to 12" so we are trying to sort that out with Harold our structural engineer. We dug the trench for the Edison's electrical conduit and will have that inspected tomorrow along with a compaction test for the footings and a walkthrough with the structural engineer for a footing design modification.

Mechanical and Building Permits




Posted by Picasa

Plumbing and Electrical Permits




Posted by Picasa

Monday, January 4, 2010

We have all permits and real work begins.

The step footings to connect the retaing footing to the other footings.

cousin dave showed up on his bike to have a look

we got two rivet busters to break down the existing wall to make way for our building block walls
Posted by Picasa